  Construction activity for August:
  • 1st floor drywall 90% hung.
  • Begin mudding 1st floor drywall the week of 8/11.
  • Begin hanging 2nd floor drywall the week of 8/11.
  • Install sprinkler drops soon.
  • Install light pole bases in parking lot soon.