Construction activity for August:
- 1st floor drywall 90% hung.
- Begin mudding 1st floor drywall the week of 8/11.
- Begin hanging 2nd floor drywall the week of 8/11.
- Install sprinkler drops soon.
- Install light pole bases in parking lot soon.
- Start up 5 RTU's for climate control soon.
|