Periodically the Aspen Group Field Construction Manager meets with church leadership to keep them up-to-date on the progress of the construction project. Here you will find a summary of what has recently been completed and what will soon begin.
Here is the current status for February 2011:
- Kitchen flooring started
- Kitchen tables & equipment started
- Kitchen equipment final connections started
- Kitchen hood system started
- Health Dept. pre-inspection
- Cabinets and Counter tops
- Start multi-purpose room flooring starte
Vinyl Base started - Entry Tile floor prep
- HVAC Testing & balancing systems
- AVL equipment & trim continued
- Door Access/ Security trim
- Acoustical Wall Panels
- Walkthrough 4-15-11 for partial building approval by Shiloh (not needed)
- AVL electrical support and cabling finished