Periodically the Aspen Group Field Construction Manager meets with church leadership to keep them up-to-date on the progress of the construction project. Here you will find a summary of what has recently been completed and what will soon begin.
Here is the current status for January 2011:
- Sheetrock hanging near complete
- Electrical rough-in in progress
- Drywall taping in progress
- Painting in progress
- Offices framed, drywalled, and taped
- Suspended ceiling grid installed on second floor